| The
Reclamation Plan <---click for plan updated as of July, 2007
Molycorp
is required under California's Surface
Mining and Reclamation Act (also known as SMARA) to develop a reclamation
plan for all mining related land disturbance at the site. The plan describes
the land area that will be affected by Molycorp's operations and how this
land will be returned to a productive use once operations have concluded
at the site.
In
addition to these requirements, there is a requirement to post a "financial
assurance" for all of the reclamation work described in the plan.
The financial assurance provides funds to complete all of the required
reclamation work at the site in the event that Molycorp is unable to do
so. Financial Assurance information must be re-calculated on an annual
basis to ensure that adequate funds are always available.
Molycorp has had an approved reclamation plan since 1977. The plan has
been updated a number of times as operations have increased and new facilities
have been added. At the present time, the plan covers reclamation requirements
for 680 acres of land at the Mountain Pass site, including roads, overburden
piles, the mine, processing / administrative facilities and ponds.
|